Alta Zinc provides June quarter update

Alta Zinc provides June quarter update

Alta Zinc (ASX: AZI) has provided its quarterly activities report for the period ending 30 June 2019.


HIGHLIGHTS

Gorno Zinc Project – Lombardy, Northern Italy

·       Pian Bracca drilling program refined and local drilling contractor selected

·       Necessary permits secured from the authorities for drilling to commence

·       Winter baseline monitoring program completed in support of the EIA

·       Advisors appointed to assist with preparation of ML renewal application

Punta Corna Cobalt Project – Piedmont, Northern Italy

·       New Balme EL awarded over the northern strike extensions of Punta Corna

·       Follow up field work planned for the July-Sept period to include:

·       Additional sampling & mapping of the mineralised lineaments

·       Petrological studies to ascertain the genesis of the mineralisation

Paterson Project, Western Australia

·       Review of existing geophysical & other historical data underway

·       Talks held with potential JV partners in relation to future planned work

Corporate

·       Cash on hand as at 30 June 2019 was approximately $2.1 million

Cardinal Resources releases June quarter activities report

Cardinal Resources releases June quarter activities report

Mali Lithium reaches final approval stage for Goulamina exploitation permit

Mali Lithium reaches final approval stage for Goulamina exploitation permit